Ofgem opens inquiry into Britain’s delayed priority grid connections
Britain’s energy regulator will examine why protected and first-phase projects are receiving later connection dates after a reform intended to clear the queue.
Press Listen to stream this report. No voice-model download or app is needed.
Britain’s energy regulator Ofgem has opened an urgent inquiry into delays in grid connection dates offered to developers whose projects were protected or placed in the first phase of a queue reform. In its November 19 announcement, the regulator said many such projects had been offered dates later than those available to them before the overhaul. It will examine the causes and compare outcomes across network companies. The announcement did not assign fault for individual delays.
The inquiry addresses a problem that a smaller queue by itself cannot solve. Clearing applications that are unlikely to proceed can free up positions on paper. An active project still needs a connection date that takes account of local network capacity, the works required and the time those works will take. A revised offer can therefore be disappointing even when its recipient remains near the front of the queue. For a developer, the gap between the old date and the new one can affect when equipment can be installed and when a project can start selling or using power.
Where the timetable slipped
The National Energy System Operator, known as NESO, says it and the network companies are still working through the remaining first-phase offers. Its public timeline acknowledges that some assessments are complex and take longer if the operator is to put credible dates, costs and conditions in an offer. That account describes one reason paperwork can take time. Ofgem is asking a broader question about why the actual connection dates offered to some customers have moved back from the dates they previously had.
The two timings are easy to confuse. One is the date on which the customer receives a revised offer. The other is the date the offer says a connection could become available. An offer can arrive on time and still list a later connection date. Understanding the difference is important when comparing reports about the reform. For a customer working to an equipment delivery schedule or ordering a site upgrade, both timings matter, but they create different risks.
How the regulator wants to improve offers
Ofgem wants more information made available about the assumptions behind the dates. It is working with government, NESO and the network companies on how to show what has changed as offers are released. More detail about the works behind a connection date would give developers a basis for discussing whether the sequence can be improved. It would also help readers distinguish a delay linked to a particular site from a group of projects waiting on the same part of the network.
The regulator also plans to look at how companies follow through once a customer accepts an offer. NESO is to check whether projects are meeting their milestones, while Ofgem is considering stronger protections for customers where a network causes delay. Those measures are at different stages. The announcement describes monitoring and ideas under examination, and it does not set a compensation entitlement for individual projects.
What the inquiry could establish
Ofgem plans to consult in December on the performance baseline for a connection incentive under its network price controls. It also intends to include connections data in an infrastructure progress report in February. The inquiry and the consultation serve different purposes. The first examines the delays already emerging in first-phase offers. The consultation would set a reference point for judging network performance in the future.
For electricity users and developers, the evidence to look for is how often dates moved, by how much and for what reason. Knowing that an offer changed does not explain whether the cause was the availability of equipment, the sequencing of network works or some other constraint. Ofgem says it can take enforcement action if the review identifies a material breach of licence obligations. That decision depends on what the inquiry finds. The immediate question is whether the regulator and network companies can explain the new dates and bring forward connections where the work can be delivered sooner.