Adani takes over project company for Bihar’s 2,400 MW Pirpainti grid link
REC confirmed the transfer of Vikramshila Power Transmission on November 21. The project will build lines and substations to carry the planned Pirpainti plant’s power into Bihar’s grid.
Press Listen to stream this report. No voice-model download or app is needed.
Adani Energy Solutions has taken ownership of Vikramshila Power Transmission, the company set up to build the high voltage network for Bihar’s planned Pirpainti power station. REC said in a stock exchange filing that its consultancy subsidiary transferred the project company’s entire shareholding, together with its assets and liabilities, on November 21. Adani confirmed the deal in its own November 22 filing. The handover moves the transmission project from the bidding process to the company responsible for developing it.
The scheme is tied to the three planned 800 megawatt units at Pirpainti in Bhagalpur district. Output from a station of that scale needs lines and substations able to move the power into the state system. The project company’s assignment is to provide that route. The transfer of shares therefore establishes who controls the transmission vehicle at this stage. Construction, testing and the ability to carry power will have to be confirmed separately.
How the power would reach the state grid
The developer’s November 19 announcement put the transmission scope at 881 circuit kilometres and 3,160 megavolt amperes of transformation capacity. Circuit kilometres measure the length of each electrical circuit. A line route can carry more than one circuit, so that number cannot be read as the distance covered on the ground. Transformation capacity describes equipment for changing voltage levels at substations. The generating station’s 2,400 megawatts describe the planned output capacity of its units.
Adani listed 400 kilovolt links from Pirpainti to Jhanjharpur and Begusarai and a further link from Begusarai to Bakhtiyarpur. It also listed 220 kilovolt connections involving Bethauli and Begusarai Town. Those parts of the scheme help explain how a network built around one generating station can connect several points in the state grid. Work on existing connections and on sites that take the new lines will matter alongside the construction of the corridors themselves.
What the winning charge covers
Bihar’s November 20 gazette records a winning annual transmission charge of 493.762 crore rupees, subject to adoption by the state electricity regulator. It identifies North and South Bihar’s distribution companies as the intended payers under the transmission service agreement, with the state transmission company acting as nodal agency. The government approval covers a 35 year arrangement and provides for the constructed assets to pass to the state transmission utility without charge after that term.
Several monetary figures in the records refer to different things. The state gazette puts the cost committee’s estimate for the system at about 3,363 crore rupees. REC separately disclosed about 18.53 crore rupees for the project company transfer, including taxes, professional fees and reimbursed expenses. The annual transmission charge is a third figure. It is the service charge offered in bidding, rather than the price paid for the project company or a tariff per unit of electricity on a household bill.
The next milestones
Adani has said it expects to deliver the transmission project in the final quarter of 2028. That target is for the network described in the company’s announcement. The stock exchange filings confirm the corporate transfer. Evidence of physical progress will come from later updates on lines and substations, and evidence of service will come when the assets are tested and energised. Those dates will matter when comparing the network’s progress with the separate development of the power station.
For Bihar’s distribution companies, the next milestones include regulatory adoption of the bid charge and the eventual availability of transmission capacity to move the station’s output. For residents and businesses, the relevant question is when the new links are ready to carry electricity across the state grid. The latest filings answer the question of ownership, while the gazette sets out how the state expects the transmission service to be paid for.
Lead source date: 22 Nov 2026 · Source check: 22 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.