CERC clears transmission-charge waiver eligibility for Ambuja’s 150 MW Rajasthan solar plant

The regulator accepted that delays at the Phalodi–Pokhran solar park kept the project from its original June 2025 deadline. The full plant entered commercial operation by the extended date of 8 August 2025.

· AI-assisted reportingPublished 24 Nov 2026Expanded / checked 24 Nov 20264 min read · 663 words
THE AUDIO EDITIONListen to this story.Natural AI narration · ready to play
0:00

Press Listen to stream this report. No voice-model download or app is needed.

Original grid illustration
Original SkyTech illustration · not an event photograph · CC0 image policy

The Central Electricity Regulatory Commission has ruled that Ambuja Cements’ 150-megawatt captive solar plant in Rajasthan qualifies for a waiver of interstate transmission charges on the same basis as a project that reached commercial operation by 30 June 2025. The order is dated 18 November 2026 and was independently reported by Mercom India on 23 November. The plant reached full commercial operation on 8 August 2025. The commission relied on an extension because delayed shared infrastructure at the solar park had kept the project from operating by its original deadline.

Ambuja developed the plant within the 750-megawatt Phalodi–Pokhran solar park to supply its own cement facilities in India. Its petition concerned the treatment of the 150-megawatt generating project under the interstate transmission charging rules. The solar park was developed by Essel Surya Urja Company of Rajasthan Limited. Central Transmission Utility of India and the park developer were both parties to the case. Those separate roles matter because the generator did not control all the work required to connect its equipment to the network.

The solar plant depended on a shared connection

A pooling station collects output from generating projects before the electricity moves onward through the network. The commission’s order records that the park’s station was charged on 8 July 2025. Ambuja said its equipment was in place earlier and that it had applied for first-time charging on 28 June. It reported commercial operation for 70 megawatts on 2 August and for the full 150 megawatts on 8 August. The order treats the readiness of the generating equipment, the charging of the pooling station and the commercial operation of the plant as separate milestones.

The order also records that the Ministry of New and Renewable Energy extended the overall park development timeline to 30 September 2025. That date applied to completing park infrastructure. Ambuja pursued its own extension in the transmission charge proceeding, where the relevant dates were the June deadline for the generation project and the August date when it reached commercial operation. The park timetable helped explain the delay. Eligibility for the waiver still had to be determined under the commission’s sharing regulations.

Three tests for an extension

The commission set out three conditions under Regulation 13(2)(h). The generating project must originally have been scheduled to enter commercial operation by 30 June 2025. Its delay must come from a qualifying event, such as transmission infrastructure being unavailable, or from a reason the generator did not cause. And the project must reach commercial operation by the extended deadline. The committee examining Ambuja’s application recommended extending the date to 8 August 2025. The commission found that the project reached full commercial operation on that date.

This distinction serves a practical purpose. A solar plant built within a larger park can depend on a substation or another shared connection that operates on a different construction schedule. Even if panels and inverters are in place, the project still needs the connection, safety and operational steps required to deliver electricity. In this case, the decision links relief to documented delays beyond the generator’s control and to the date the entire capacity actually entered service.

What the decision covers

The operative finding applies to the Ambuja project under the specified interstate transmission rules. It deals with eligibility as if the relevant June date had been met. The order does not put a rupee value on the waiver or report a new generation addition in November. Its immediate effect concerns the treatment of an already commissioned project. Industrial consumers following similar cases need to distinguish the renewable capacity available to serve their facilities from the network charges that may apply when that electricity is carried to a different location.

For projects with common infrastructure, the records that mattered in this ruling included the original schedule, the reason the shared connection was delayed, the committee’s recommendation and proof of commercial operation by the extended date. A capacity announcement alone would not have answered those questions. The decision shows how the regulator used the project’s commissioning record to reach a finding specific to the facts before it.

Sources & backgroundMercom India’s 23 November report on the Rajasthan solar waiver ↗Central Electricity Regulatory Commission decision of 18 November 2026, Petition 135/MP/2026 ↗

Lead source date: 23 Nov 2026 · Source check: 24 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.