India opens more grid connection options for renewables and storage outside solar hours
CERC’s fourth grid-access amendment lets eligible projects seek spare capacity at additional substations outside solar hours and requires monthly updates on available margins.
Press Listen to stream this report. No voice-model download or app is needed.
India’s Central Electricity Regulatory Commission has widened the options for renewable power and storage projects seeking to connect to the interstate grid outside solar hours. The fourth amendment to the 2022 connectivity and general network access rules is in Gazette of India issue 686, dated November 19. It allows qualifying projects to seek access at additional substations where the existing network has spare capacity during those hours. The Central Transmission Utility of India is to publish and update the available margins monthly.
A grid connection can be more useful at some hours than others. A solar project generally sends its power out while the sun is up. A battery can save some electricity to deliver later, while wind generation follows different patterns at different sites. If several projects seek the same network capacity at the same time, the grid must be able to handle their combined output. A connection limited to certain hours can give a project a way to use capacity that is available for only part of the day.
How projects can seek spare grid capacity
Under the new route, a renewable generating station or storage system can apply with at least 50 megawatts of installed capacity. Projects can also meet that size in aggregate through a lead generator or lead storage provider. Applications are assessed against the available margin. The Gazette rules out expanding the interstate transmission system to accommodate applications under this particular route. This makes the suitability of the chosen substation central to whether a project can use it.
The amendment also lets an applicant consent in writing to switch between a request for full-day connectivity and one for solar-hours or non-solar-hours access, if the margin declared during consultation supports the alternative. That flexibility could matter to projects that can deliver electricity profitably during part of the day. Moving to a narrower time window changes the likely hours of delivery, which may change the value of an agreement with a power buyer.
How access hours affect battery projects
The storage provisions also distinguish power capacity from energy capacity. For storage seeking connectivity under Regulation 4.1(c), the amendment specifies a minimum energy rating in megawatt-hours equal to twice the power rating in megawatts, unless the Central Electricity Authority specifies a different level for system needs. A 50-megawatt system would therefore correspond to at least 100 megawatt-hours under that default ratio. In simplified terms, that energy rating is equivalent to two hours of output at the rated power, before accounting for operating limits and losses.
For a buyer, two projects with the same megawatt rating can offer different services. A high power rating helps a project deliver a large amount of power at a given moment. More energy capacity allows delivery to continue longer. In addition, a battery’s ability to discharge and its permission to put electricity onto the network are separate facts. A buyer assessing an evening supply offer therefore needs to know both the energy the battery can deliver and the hours its connection permits.
What to watch in the monthly updates
The utility’s monthly list will show where it has identified spare capacity under the amendment. It is an early indicator for developers comparing sites. A project still needs to proceed through the connectivity process and comply with the terms of any grant. The notified procedure also calls for agreements governing shared use of the dedicated transmission system under the new route. Site comparisons therefore need to account for the cost of reaching the connection point and any applicable sharing arrangements.
The practical test will be whether spare capacity listed at specific substations matches where developers can build and where buyers need electricity. A monthly margin can help a developer decide where to investigate. The subsequent connectivity grant and the delivery terms agreed with buyers will show how much of that capacity can translate into scheduled power. Those milestones will be more informative for buyers than an estimate based on a project’s installed capacity alone.
Lead source date: 19 Nov 2026 · Source check: 22 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.