Statkraft signs eight-year deal for Zelestra’s 700 MWh battery in central Italy
The deal covers the full capacity of a planned four-hour battery connected to a Terna substation. Zelestra expects the project to enter service in 2028.
Press Listen to stream this report. No voice-model download or app is needed.
Zelestra and Statkraft have signed an eight-year agreement covering the full capacity of a planned grid battery in central Italy, the developer announced on 26 November. Zelestra will build and operate the 175-megawatt plant and expects it to enter service in 2028. The facility will connect to an existing substation operated by Italy’s transmission company, Terna. Zelestra says the project has obtained its authorisations.
The planned installation can store 700 megawatt-hours. Dividing that capacity by its 175-megawatt power rating gives a nominal discharge duration of four hours. That distinction is useful when comparing storage projects. Power describes how quickly a battery can deliver electricity. Energy capacity describes how much it can hold for discharge. The figures give an engineering benchmark, while the amount delivered in any particular period will depend on how the battery is operated.
What the two companies will do
Zelestra described the contract as a physical tolling agreement. Under the arrangement, the developer will take care of the infrastructure and Statkraft will use its trading and optimisation capabilities to earn revenue from operating the battery across eligible markets. That division gives each company a different job. Keeping the equipment available is an engineering responsibility. Deciding when to charge, when to discharge and when to reserve capacity for another market comes down to operating conditions and prices.
A four-hour system can move electricity from one part of a day to another. For example, a battery may charge when abundant renewable generation coincides with relatively low demand. It can then discharge later if electricity becomes scarcer. Those decisions are conditional on market prices, network constraints and how much charge remains. Operators must also account for energy lost during charging and discharging when judging whether a trading opportunity is worthwhile.
Energy-Storage.News confirmed the reported size, term and indicative start year. It reported that the contract is Statkraft’s first tolling deal in southern Europe and Zelestra’s fourth in Italy. The announcement does not specify the price Statkraft will pay, the exact substation or the project’s construction timetable. Those omissions limit comparisons with other assets. A four-hour rating alone tells readers little about the fees, availability requirements or other obligations that determine a contract’s value.
A separate route to market from Terna’s auction
The announcement comes in the same week as Terna’s second auction under Italy’s electricity storage procurement mechanism, known as MACSE. On 24 November, Terna announced awards totalling 16 gigawatt-hours across southern Italy and the islands at a weighted average of €11,382 per megawatt-hour per year. It confirmed the results on 26 November. The auction’s contracted facilities are scheduled for 2029, a year after the target Zelestra gave for its privately contracted battery.
Those announcements show two ways storage projects can secure a long-term customer. Terna’s auction uses a regulated process to buy capacity for a defined area and delivery year. In central Italy, Zelestra and Statkraft negotiated their contract directly. The auction figure applies to the capacity Terna procured. The private agreement’s financial terms would be needed to compare its economics with the published auction results.
The two time horizons matter for the system as well as the companies. Terna’s awards set out a capacity commitment for a future delivery year, measured in stored energy. The private deal gives a single market participant access to one identified plant for eight years. Each arrangement allocates responsibility for how the capacity will be made available. Neither announcement establishes how often individual batteries will charge or discharge once they are running.
What to watch before the battery opens
For Italy’s power system, the milestones ahead include construction, connection and commercial operation. Grid-scale storage can give the system more options when electricity production and consumption move in opposite directions, including as solar output tapers in the evening. The flexibility available from this project will depend on its operating limits and market participation once it opens. For now, the reported milestone is a signed contract covering the full planned battery, with 2028 the developer’s target for service.