L&T wins order for 900 MWh, three-hour battery system at Khavda

Larsen & Toubro says its renewables and electronics businesses will develop the 300 MW system in Gujarat. The release identifies liquid cooling and leaves the customer and commissioning date undisclosed.

· AI-assisted reportingPublished 26 Nov 2026Expanded / checked 26 Nov 20264 min read · 635 words
THE AUDIO EDITIONListen to this story.Natural AI narration · ready to play
0:00

Press Listen to stream this report. No voice-model download or app is needed.

Original storage illustration
Original SkyTech illustration · not an event photograph · CC0 image policy

Larsen & Toubro said on 25 November that two of its businesses had jointly won an order to develop a 300-megawatt battery at Khavda in Gujarat. The system is designed to store 900 megawatt-hours. L&T described the contract as significant, a classification it uses for orders worth between 1,000 crore and 2,500 crore rupees. It did not give an exact price or identify the customer in its release. ETEnergyworld and Financial Express independently reported the order and the two capacity figures. The announcement concerns a project to be developed, so it does not add 300 megawatts to the grid’s available battery capacity today.

The award brings together L&T’s renewables business and L&T Electronic Products and Systems. In its announcement, the company presented the two groups as joint recipients of the work. It did not allocate individual engineering or construction responsibilities in the published release. It did say the installation would use liquid cooling. Battery equipment generates heat when it charges and discharges, and a cooling system helps keep its cells within their operating temperature range. L&T said the approach would support a compact design, safety and operating life. Those are design aims in the announcement. Actual performance will depend on the equipment installed, how the project is tested and what happens in operation.

What a three-hour rating means

The ratings show what a three-hour system means. The 300-megawatt figure describes how much power it is designed to deliver at a given time. The 900-megawatt-hour figure describes the amount of energy it can hold at the stated rating. Dividing the second figure by the first gives a nominal three hours of discharge at rated power. A shorter discharge at that power would use less of the stored energy. Delivering at a lower rate could spread available energy over more time, subject to the operating limits and losses of the equipment. The headline figures are design ratings rather than a prediction that the battery will run at its maximum output on every dispatch.

Storage at Khavda can help move the use of renewable electricity from the hours when it is generated to the hours when the grid needs it. L&T said it expects the system to store excess renewable output and release it in periods of high demand. For a grid operator, the timing of that service matters because a surplus in one part of the day can coexist with a shortage later. The battery can absorb or deliver power within its ratings, but it needs a source of charging energy. It does not generate new electricity. The announcement does not specify how often the buyer expects to cycle the battery or which plants will supply the charging power.

Reading the Khavda announcements separately

Several procurement announcements refer to Khavda. A separate November filing by Pace Digitek identified two 900-megawatt-hour blocks awarded by NTPC Green Energy within a larger project there. The L&T release does not identify its order by the same procurement or block numbers. Similar capacity figures and a common location do not establish that two disclosures describe the same installation. They also do not establish that every announcement can be added together to calculate how much storage will eventually operate at Khavda. The available descriptions are sufficient to report L&T’s particular award and its stated design, while the customer and contractual relationship remain unclear.

What the award leaves open

The next details that would make this order comparable with other storage projects include the scheduled commissioning date and the testing requirements at the point of connection. The company did not publish either in this release. Delivery of batteries, completion of associated electrical work and successful operation as an integrated plant are separate milestones after an award. Readers can follow those steps as they are disclosed. For now, the firm information is the size and duration of the planned installation, the two groups involved and L&T’s choice of cooling technology.

Sources & backgroundETEnergyworld, 25 November reporting on the L&T award ↗Larsen & Toubro’s 25 November award announcement ↗Financial Express, independent coverage of the L&T award ↗Pace Digitek’s separate NTPC Green Energy order, NSE filing dated 16 November ↗

Lead source date: 25 Nov 2026 · Source check: 26 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.