Detailed news report
Uttarakhand seeks fresh bids for 102.5 MWh of battery storage at six substations
UPCL’s November listing sets a December 4 deadline for its Cluster C tender. The batteries would serve substations in Uttarkashi, Haridwar and Tehri.
Press Listen to stream this report. No voice-model download or app is needed.
Uttarakhand Power Corporation Limited is seeking bids to develop battery storage across six distribution substations. The state’s procurement portal lists the new Cluster C tender under reference CCP-I/49/2026-2027, with bids due by 5 p.m. Indian Standard Time on December 4 and opening scheduled for noon the following day. The project combines 41 megawatts of output capacity with 102.5 megawatt-hours of energy storage. Mercom India independently reported the December 4 deadline on November 20.
The state portal published the listing on November 18. In its request for proposals, the utility calls for a developer to build, own and operate the systems and compete on a capacity charge. That structure puts the storage service at the centre of the procurement. The winning bidder would provide batteries at the distribution network locations identified by the utility, with the installations drawing energy to charge and returning it to the network when scheduled.
Where the batteries would connect
The bid document tentatively assigns 20 megawatts to two sites in Uttarkashi, 16 megawatts to three sites in Haridwar district including one in the Roorkee area, and five megawatts to Rajakhet in Tehri. The figures come from the site table in the tender, which says bidders should confirm the locations and capacities through surveys and coordination with UPCL. Saur Energy separately identified the same six substations in its coverage.
At their combined rated output, 102.5 megawatt-hours divided by 41 megawatts represents two and a half hours of discharge on paper. Megawatts describe how quickly a battery can deliver electricity and megawatt-hours show how much it can deliver over a period. Saur Energy reported that the operating specification calls for two daily charge and discharge cycles, with discharge windows during both morning and evening peaks. The batteries need time and available electricity to recharge between uses.
How local storage would be used
Placing batteries near distribution substations gives the utility several points at which to shift the timing of electricity supply. Charging in a lower-demand period and discharging later can reduce the power a substation needs from upstream lines in a peak window. The amount depends on how the battery is dispatched, the demand on connected circuits and whether the site has enough room to charge at other hours. Each substation’s experience can therefore differ even under one procurement. Several smaller installations also let planners compare performance across different load profiles. A substation with a short, sharp peak creates a different operating problem from one where electricity use stays high for much of the evening.
Under the proposed structure the developer would take on design, financing, installation and operation. UPCL would make substation land available through a right of use. Saur Energy’s reading of the bid document puts the commissioning window at 12 months from the agreement’s effective date or land handover, whichever comes later. Those milestones matter because assigning an installation to a substation on paper is only the first step toward an operating connection.
What the latest bid window establishes
An October report identified a partnership involving Jupiter Wagons’ energy business and Madhav Infra Projects as the lowest bidder in an earlier Cluster C process with the same aggregate capacity. A November investor presentation filed with the National Stock Exchange also lists that Uttarakhand capacity as won. The new procurement listing establishes an active bid window under its own tender reference. The records reviewed leave the contractual status of the earlier process unresolved.
The tender’s next public milestones are the bid deadline and opening, followed by the procurement result and signed storage agreement. Once the contracts and final sites are confirmed, commissioning records can show when each substation is ready to use its batteries. For electricity users, the eventual measure of the project is how much storage the local network can actually call on during morning and evening peaks.