India and Nepal lay foundation stone for 669 MW Lower Arun hydropower project
SJVN’s project in eastern Nepal is designed to reuse water from the upstream Arun-3 plant. The developer is targeting the 2030–31 financial year for commissioning.
Press Listen to stream this report. No voice-model download or app is needed.
India and Nepal laid the foundation stone for the 669-megawatt Lower Arun hydropower project on November 23, giving the proposed plant in eastern Nepal a public milestone during Prime Minister Balendra Shah’s visit to New Delhi. Shah and Indian Prime Minister Narendra Modi took part remotely from the Indian capital, according to the joint statement issued after their talks. The plant, being developed by a subsidiary of India’s state-owned SJVN, is planned for the Arun River in Sankhuwasabha and Bhojpur districts. SJVN said its local event brought project staff together with Nepali government, community forest and municipal representatives.
The ceremony comes at a point when construction contracts and financing are moving on different schedules. SJVN said it had awarded major packages and that construction activities were under way. The Kathmandu Post reported that financial closure remained pending and quoted Investment Board Nepal’s chief executive as saying the physical groundbreaking would occur in Nepal. The financing milestone will show when the funding arrangements needed to support the project are in place. Monday’s ceremony did not establish that they had been completed.
Two power stations will share the same water
Lower Arun’s design depends on the 900-megawatt Arun-3 plant upstream. SJVN plans to send water discharged from the upstream station through a tunnel about 17.4 kilometres long to a second powerhouse, where four generating units would use it again. SJVN says the configuration avoids the need for a separate storage reservoir for Lower Arun. The same water can generate power at each station because it drops in elevation twice, through two sets of turbines.
That configuration also ties the two projects together. The volume and timing of water arriving from the upstream plant will help determine how much the downstream station can generate. The 669-megawatt figure is the design capacity at a given moment. SJVN’s annual estimate of about 2.9 billion kilowatt-hours describes a different measure: how much energy it expects the station to produce over a year. Actual annual production will depend on the water available and on both stations being able to run as planned.
Financing, schedule and Nepal’s share
SJVN’s exchange disclosure put the estimated cost at about 5,792 crore Indian rupees and identified the 2030–31 financial year as its commissioning target. Both are estimates at this stage. Tunnelling, work at the powerhouse and testing each have to be completed before that target can turn into a commercial operating date. Progress on a construction package can therefore be significant without settling the timetable for the whole plant.
The developer says the project agreement gives Nepal 21 percent of the electricity it generates free of charge. That provision refers to a share of energy produced, so the amount delivered will vary with output. The plant is being developed under an arrangement in which the project company will build, own and operate it before transferring it. Those arrangements describe Nepal’s entitlement and the project’s ownership model alongside the engineering plans.
Cross-border lines are at a separate stage
The two governments also reported progress in forming joint ventures for two high-capacity cross-border links, one between Inaruwa and New Purnea and the other between Dodhara and Bareilly. Those corridors are separate from the Lower Arun powerhouse. The statement did not say the lines had entered service, and the existence of an interconnection does not in itself determine how much power a particular plant can sell through it. Commercial arrangements and available grid capacity will still matter.
What can be checked next is whether financial closure is announced, how the tunnel and powerhouse contracts proceed, and whether the two countries publish concrete steps on the transmission ventures. Together those milestones will give a clearer picture of when the new station could generate power and how Nepal’s expanding electricity trade with India could accommodate it.