Bids due 25 November for Haryana’s 500 MW solar and battery tender
Haryana’s two distribution utilities are seeking solar power backed by a 250 MW battery system. The tender sets out how the state would draw stored energy during four selected peak hours each day.
Press Listen to stream this report. No voice-model download or app is needed.
The Haryana Power Purchase Centre is due to close bids at 3 p.m. on Wednesday, 25 November, for 500 megawatts of solar power backed by battery storage. The procurement centre, which buys on behalf of the state’s two distribution utilities, moved the deadline in a notice issued on 12 November. It lists bid opening on 27 November. The request was first issued in October. The approaching deadline offers a closer look at the service Haryana wants to buy and what still has to happen before the state can use it.
The buyers are Uttar Haryana Bijli Vitran Nigam and Dakshin Haryana Bijli Vitran Nigam. The tender calls for projects within Haryana with a combined 250 megawatts of battery output and 1,000 megawatt-hours of energy capacity. Mercom India reported the procurement when it was issued. The state’s revised schedule gives developers more time to submit their offers and bid security. The dates in the amendment concern submissions and opening bids. The original document lists the price stage and any reverse auction separately.
What the batteries are meant to deliver
An ordinary solar purchase largely follows the hours when panels can generate. A battery lets some of that energy be moved to a different part of the day. That can matter when many customers still need power after solar output has fallen. The tender’s two battery figures describe different things. The power rating tells the buyer how much the batteries can deliver at a given moment. The energy rating tells it how much electricity can be delivered across the selected period. At the listed ratings, 1,000 megawatt-hours corresponds to four hours of discharge at 250 megawatts.
The draft agreement gives the buyer a scheduling role. Haryana can choose four peak hours between six in the evening and nine the following morning. The tender also requires at least one continuous hour of battery discharge within the chosen schedule. This lets the utilities decide when stored energy would be most useful within that window. The project operator would have to plan charging accordingly. A schedule focused on an evening rise in demand could differ from one that calls for some energy before a cold morning.
The value of that flexibility depends on what the buyer would otherwise have used in those hours. For example, shifting output can help if power is cheaper or more plentiful earlier in the day and harder to obtain later. Charging and discharging also consume some energy, and equipment must remain available as it ages. Buyers comparing this kind of bid therefore have reason to look at reliability, duration and timing as well as the headline solar capacity. A megawatt of panels and a megawatt of battery output serve different parts of the purchase.
What the opening of bids will tell Haryana
Opening bids is an early test of developer interest. It does not establish a final purchase price, name a supplier or bring equipment into service. The tender provides for competitive tariff discovery and envisages a twenty-five-year purchase agreement following tariff adoption by the Haryana Electricity Regulatory Commission. Later public milestones could show whether the state obtained offers for the full capacity, the terms on which it selected projects and when the projects would be expected to start supplying power.
For electricity users, the eventual question is how the new supply would fit into the utilities’ broader portfolio. A battery can help cover a portion of peak demand, but service at a particular home or business also depends on the local distribution network. The near-term milestones are the submission and opening dates. The contract and commissioning stages will show how much of the proposed capacity moves from the procurement papers to the grid. Until then, the tender describes an intended purchase, with the actual amount and price still to be established through the competition.