APA starts work on Mount Isa solar farm and 104 MWh battery
Construction has begun on the Sybella Creek project in north-west Queensland, where 72 MW of solar and a two-hour battery will serve a regional grid that still relies on gas for firm supply.
Press Listen to stream this report. No voice-model download or app is needed.
APA Group has started building a 72-megawatt solar farm and a 104-megawatt-hour battery near Mount Isa in north-west Queensland. In a company update, the Australian energy infrastructure operator said it marked the start with the Kalkadoon Traditional Owners, its mining customer and its construction partner. Energy-Storage.News reported the milestone on 24 November, following earlier local trade coverage. The company is targeting electricity deliveries from mid-2028. For now, the change at Sybella Creek is that work has moved from investment approval into construction.
The project is backed by an electricity supply agreement with Ernest Henry Mining, part of Evolution Mining, running until mid-2046. APA announced its investment decision in August and put its commitment at 259 million Australian dollars. Evolution Mining separately acknowledged its involvement in the project at its Ernest Henry operations. Engineering contractor UGL said in September that its contract covers the design, procurement, construction and commissioning of both the solar plant and the battery. Each announcement describes a different stage in bringing the equipment into service.
How solar, storage and gas fit together
The battery is rated at 52 megawatts of power and 104 megawatt-hours of stored energy. The first number indicates how quickly the equipment can deliver electricity. The second indicates the amount of energy it can hold. Taken together, the ratings correspond to two hours at full rated output on paper. Actual dispatch depends on how much charge is available and how the system is run. The solar farm has its own 72-megawatt rating, and daylight and weather will shape how much it produces at any given time.
APA says the existing gas-fired Diamantina station will continue to provide firming under the supply agreement. That matters for a mining operation whose demand can continue through the night or through stretches of weak solar production. Stored electricity can cover part of the difference between strong daytime solar output and later demand. The gas station remains available when the combination of solar and stored energy cannot cover the contracted supply. The parties have not reported measured fuel savings from Sybella Creek, since the new equipment is still being built.
APA identified the site as land owned by the Kalkadoon Traditional Owners and said their representatives joined its team at the construction milestone. Evolution Mining and UGL were also represented, according to APA. Their respective roles are distinct: the mine supplies the long-term commercial basis for the project, while UGL is responsible for delivering the new equipment. Starting site work leaves the actual performance of the system, including how smoothly the battery and gas plant operate together, to be demonstrated during commissioning and subsequent operation.
A project for the grid that exists today
The North West Power System is separate from Australia’s National Electricity Market. That makes local generation and power balancing especially important in the region. CopperString, a separate planned transmission project, would link the area to the wider network if its western section is completed. The Queensland Audit Office describes an eastern link from Townsville to Hughenden and a western link onward to Mount Isa. It identifies enabling work on the western section. Those preparatory steps are a different development from the construction now reported at Sybella Creek.
For the region, Sybella Creek offers a way to add daytime renewable production and shift some of it to later hours using equipment located on the existing power system. For other remote industrial grids, the project will be worth watching because it combines a customer with a long-term contract, new storage and a source of backup power already in service. The next milestones are installation of the equipment, testing of its response alongside Diamantina and confirmation of when regular deliveries start. The date matters to the mine because construction and testing must be completed before the new assets can support its day-to-day demand.