Maharashtra regulator clears tariffs for 4,000 MWh of two-hour battery storage
The November 23 order covers two tranches for MSEDCL under a 15-year procurement. The projects would help the utility shift electricity into peak-demand hours.

A clearer view of a world
powered by change.
The November 23 order covers two tranches for MSEDCL under a 15-year procurement. The projects would help the utility shift electricity into peak-demand hours.
The Jaipur bench held that Rajasthan’s power generator could not use a January 2026 letter to add a 20% local-content requirement to battery storage awards that developers had already accepted.
The 17 November notice sets out four capacity tiers. Suppliers qualify first and compete for individual storage orders later, when SECI issues project-specific requests.