Wokingham starts Barkham solar farm works with grid connection due from September 2027

The UK council has begun preparing the site for its 30 MW solar farm. Panel installation is due to start in 2027, and design and routing work continues with the network operator.

· AI-assisted reportingPublished 24 Nov 2026Expanded / checked 24 Nov 20263 min read · 600 words
THE AUDIO EDITIONListen to this story.Natural AI narration · ready to play
0:00

Press Listen to stream this report. No voice-model download or app is needed.

Original solar illustration
Original SkyTech illustration · not an event photograph · CC0 image policy

Wokingham Borough Council said on 24 November that preparatory work had started at Barkham Solar Farm, a council-owned project in Berkshire, England. The first activities include making an entrance to the site and setting up the construction compound. The council expects the main installation programme to begin in 2027. It said Scottish and Southern Electricity Networks had confirmed that the project could connect from September 2027, giving the council and contractor Equans a date to plan around.

The council said the connection offer addresses both the distribution and transmission elements of the project. Detailed work on the design and route is still to be agreed with the network company. The council has previously attributed a delay to changes in how Britain arranges grid connections. Its latest update gives a window for connection and distinguishes that milestone from the site preparation currently taking place.

What is starting on site

Equans describes Barkham as a 30 megawatt solar farm. The site is on council-owned farmland north of California Country Park, between Barkham and Finchampstead. The company was appointed to build the project in September. The current sequence starts with access and other preparations before panels and associated equipment are installed. Local residents may therefore see construction traffic before there is any equipment in place to generate electricity.

In its November update, the council estimated that the farm would produce about 28,500 megawatt-hours per year once running. Megawatts describe the rated power of the solar farm. Megawatt-hours describe how much electricity it is expected to produce over a period. Actual annual output will depend on weather, the availability of the equipment and how much power the network can accept at different times. The council says the electricity generated will go into the grid.

The timing of a network connection matters even after a developer has a site and a contractor. A solar farm needs the relevant connection equipment and arrangements for safely exporting power. If construction finishes ahead of a connection, the equipment can be ready while the project is still waiting to sell electricity. If construction takes longer, the network date alone cannot bring forward generation. Barkham’s connection date gives both sides a shared target while the remaining work proceeds.

How the council will judge the project

The council also expects the project to generate an annual surplus of more than one million pounds after financing costs. That is the council’s forecast for an operating project. It says the income would help support local services. How much becomes available in any particular year will depend on actual generation, revenues and expenses. The construction announcement gives the public an opportunity to follow these estimates alongside the dates for building and connecting the farm.

For a local authority, work on a power project also raises questions that sit outside the electricity forecast. The plans for access affect where construction traffic enters. The eventual connection route determines where some of the work will take place away from the panel site. These are distinct parts of the job, and the council’s notice says routing details will be worked through as it progresses. Local updates can show which work is due and when it will affect residents.

The milestones to watch are the start of panel installation, completion of the connection works and the first export of electricity. Each will supply a different piece of evidence about how the schedule is holding up. After that, annual metered generation and the council’s published accounts will show whether the farm is delivering the electricity and income forecast in the November update. For now, the project has moved into early work on site with September 2027 as the stated window for connection.

Sources & backgroundWokingham Borough Council, 24 November site works and connection update ↗Equans, contractor announcement and project capacity ↗Wokingham Borough Council, decision on the construction contract ↗Wokingham Borough Council, project background ↗Reading Dispatch, 24 November coverage of the start of work ↗

Lead source date: 24 Nov 2026 · Source check: 24 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.