US extends winter order keeping two Pennsylvania generating units available
The Department of Energy directed PJM and Constellation to keep Eddystone Units 3 and 4 available through February 18. The order limits dispatch to hours needed to meet the emergency.
Press Listen to stream this report. No voice-model download or app is needed.
Two generating units at the Eddystone station in Pennsylvania will remain available to the regional grid operator through February 18 under an emergency order issued by the US Department of Energy. The November 20 decision directs PJM Interconnection and plant operator Constellation Energy to keep Units 3 and 4 ready to operate. The new order took effect on November 21 after an earlier order ended the previous day. The department first intervened in May 2025, when the units were approaching their planned retirement.
The distinction between availability and generation matters for electricity customers. A unit can be able to run while supplying no electricity during many hours. The order tells PJM to use economic dispatch and call on the units only during periods needed to meet the emergency. It leaves PJM to determine when those periods occur. A winter with few dispatch calls could therefore produce a very different outcome from one in which severe conditions require repeated operation.
Availability and generation measure different things
The Federal Energy Regulatory Commission’s November winter assessment lists the two units at a combined 760 megawatts under the previous arrangement. That figure describes generating capability. It gives no indication of how much energy the units will produce by February, a quantity that depends on their operating hours and output. The new order also excludes them from treatment as a capacity resource, a separate category PJM uses when planning how much supply will be available to meet future demand.
In its own winter outlook, PJM said it expected to have adequate supplies under the most likely conditions. The operator also said its margin for dealing with unexpected problems has tightened as demand grows and new supply takes time to arrive. Those two findings can coexist. For instance, a system may have enough resources on a normal cold day and still have less protection against an unusually long cold spell combined with substantial outages at generators elsewhere in the region.
What PJM must report
The new order requires PJM to tell the department daily whether the Eddystone units operated. It also asks PJM for a description of the steps taken or planned to keep them available by December 5. The order calls for compliance with applicable environmental controls as far as feasible in emergency operations. It also preserves obligations to pay fees or obtain offsets or allowances for emissions where applicable. Those terms make the record of actual dispatch relevant for evaluating the decision’s environmental effects.
Environmental and consumer organisations, including the Natural Resources Defense Council and Public Citizen, sought rehearing of the prior August order in September. Their filing challenged a previous extension. It supplies context for the recurring debate over how long federal emergency authority should keep plants available after retirement was planned. The November document sets its own end date, and the earlier filing by itself does not establish what will happen if the department is asked to renew the order again.
What the order means for costs
The department’s direction on costs also concerns two distinct decisions. PJM is to consider operating costs when dispatching available resources during the emergency. Constellation can separately seek tariff changes or waivers from the federal regulator as needed. The November decision states that a mechanism for recovering costs is available under federal law. Any concrete effect on consumer bills will depend on how that mechanism is applied, as well as the cost of making the units available or operating them.
The December report and PJM’s dispatch notices give readers ways to follow the order through the winter. The first can show what the operator did to keep the units available. The daily record can show whether PJM actually needed their electricity. Together they can help distinguish the role played by the temporary order from the resources PJM plans to rely on under ordinary winter conditions.