ReNew and Purvah win Noida Power’s 300 MW round-the-clock renewable auction

The two bidders quoted ₹4.43 and ₹4.44 per kWh for a combined 300 MW. The procurement pairs renewable generation with storage under planned 25-year contracts.

· AI-assisted reportingPublished 25 Nov 2026Expanded / checked 25 Nov 20264 min read · 626 words
THE AUDIO EDITIONListen to this story.Natural AI narration · ready to play
0:00

Press Listen to stream this report. No voice-model download or app is needed.

Original storage illustration
Original SkyTech illustration · not an event photograph · CC0 image policy

Noida Power Company Limited’s auction for 300 megawatts of round-the-clock renewable supply produced two winning bids separated by one paisa per unit. ReNew Private Limited secured 85 megawatts at ₹4.43 per kilowatt-hour and Purvah Green Power Private Limited secured 215 megawatts at ₹4.44, according to results reported by pv magazine India and Renewable Watch on 25 November. The Greater Noida distributor plans to buy power under 25-year agreements, with delivery from renewable projects linked to the interstate transmission network.

Seven developers offered a combined 695 megawatts, according to SolarQuarter. That is more than twice what Noida Power was buying. The two awarded blocks fill the tender entirely, and weighting the two bids by their capacity produces a price of about ₹4.44 per kilowatt-hour. That calculation describes the reported bids. The quoted figures relate to the procurement, while the rate a customer pays is determined through the applicable retail tariff process.

What the regulator approved

The auction followed the Uttar Pradesh Electricity Regulatory Commission’s order in Petition 2418 of 2026. The commission agreed that the distributor needed long-term firm capacity to meet anticipated demand and approved procurement through competitive bidding. It also permitted a single bidder to take the full 300 megawatts at the lowest discovered tariff. If the full quantity could not be allocated on that basis, the order allowed capacity to be filled from bids priced within two percent of the lowest offer. The outcome reported this week split the purchase between two developers.

The order addressed a separate risk that bid prices alone cannot resolve. Developers needed a final grid connectivity grant at the point of bidding, with a connectivity start date by the end of December 2028. The commission’s reasoning was that a project with only a pending application or an in-principle approval could struggle to secure the link before supply was due. For a buyer contracting power years in advance, the ability to move electricity onto the grid is part of whether a project can deliver on schedule.

The commission also allowed bidders to arrange storage from a third party. It required evidence of the arrangement and left the renewable developer accountable for its obligations under the power purchase agreement. That distinction matters when one company generates electricity and another operates storage. The distributor can still hold its contracting developer responsible for contracted performance even if the storage operator causes a shortfall.

How storage changes the supply contract

Conventional renewable contracts often focus on the energy a plant can generate when conditions are favourable. In a round-the-clock procurement, the delivery profile matters as well as the accumulated units. Energy stored in one part of the day can help serve demand later, after solar output has fallen. A developer can also combine generation from different sites and technologies. How well those sources complement one another determines how much storage the developer must arrange and how frequently it has to draw on it.

The 300-megawatt headline refers to the capacity in the procurement. It cannot be used on its own to calculate the size of a battery, a figure normally measured in megawatt-hours, or the annual amount of electricity delivered. Both depend on the design of the individual projects and their delivery obligations. The regulatory order and the reported auction results establish the framework and the bid prices. They leave project-level details such as the storage capacity behind each award to subsequent disclosures.

What to watch before delivery begins

Renewable Watch reported that supply is expected in the 2028–29 financial year. The regulatory order records a December 2028 start in the distributor’s proposal. The developments that will show whether that timeline holds include contract execution, project and storage arrangements, and grid readiness. This week’s auction fixes the reported allocation and prices for the planned supply. Actual delivery will be measured once the generators and their storage arrangements are in service.

Sources & backgroundpv magazine India ↗Uttar Pradesh Electricity Regulatory Commission procurement and bidding order, Petition 2418 of 2026 ↗Renewable Watch auction result and reported start window ↗SolarQuarter auction result and bidding participation ↗

Lead source date: 25 Nov 2026 · Source check: 25 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.

#RenewableEnergy #GreaterNoida #EnergyStorage #PowerProcurement

Corrections: skytechdestination@gmail.com. Please include this article’s link and supporting evidence.