Gujarat regulator orders wind project penalties recalculated, upholds partial termination
GERC gave Solarcraft Power India 3 limited relief on commissioning delays at a 200 MW project in Gir Somnath. Gujarat Urja Vikas Nigam can retain termination compensation for the 38.3 MW left uncommissioned.
Press Listen to stream this report. No voice-model download or app is needed.
The Gujarat Electricity Regulatory Commission has ordered Gujarat Urja Vikas Nigam Limited to recalculate delay penalties for a 200-megawatt wind project in Gir Somnath. The commission allowed some extensions for Solarcraft Power India 3 after examining why construction and commissioning slipped at individual sites. It upheld the termination notices and compensation for the 38.3 megawatts that did not come into service. Mercom India independently reported the 20 November ruling on 23 November.
The two companies signed the power purchase agreement in December 2022. The first scheduled commercial operation date was 13 December 2024. Extensions previously granted by the buyer moved that date to 10 April 2025. Solarcraft brought 161.7 megawatts into service and disputed the deductions made from its invoices as well as the separate charge for the portion that never entered service. The commission treated those claims differently because the agreement applies different remedies to delayed delivery and capacity that remains missing past the contractual deadline.
Different dates apply to different parts of the project
The commission moved the general scheduled date to 16 May 2025 and the corresponding long-stop date from 7 October to 12 November 2025. Its decision also assessed individual clusters and their commissioning records. That matters for the buyer’s calculation. Turbines that entered service on different dates may have different numbers of chargeable days. The order directs the buyer to calculate the amount using the revised dates applicable to each site or cluster.
For example, the commission kept the 16 May date for the Pranchi cluster and recorded that its six units, with a combined capacity of 19.8 megawatts, entered service in stages from 26 September to 5 October 2025. That timetable still left delays after the date the commission recognized. The order discusses individual obstacles under the agreement’s provisions for exceptional events outside a party’s control. In the case of a revised grid bay layout at Pranchi, the commission found that the developer had delayed starting work after the original layout approval and rejected relief on that ground.
Why the compensation for missing capacity stands
The uncommissioned 38.3 megawatts included 23.1 megawatts planned at Bhetali. The order says the developer had not identified an exceptional event specific to that location and that the planned capacity there had been abandoned. More broadly, the commission held that the delay grounds it accepted elsewhere did not explain the failure to bring the entire remaining capacity online. The buyer’s default notice used the earlier long-stop date, but the commission upheld it because the shortfall continued after the revised date as well.
The ruling allows Gujarat Urja Vikas Nigam to retain about 18.54 crore rupees in termination compensation for that shortfall. It also holds the developer liable for delay damages on the uncommissioned capacity for the contractual 180-day period. The commission rejected the developer’s request to quash the March default notice and May termination notice. It disposed of the interim applications alongside the final decision.
What the buyer has to recalculate
For the capacity that did come online, the next step is an accounting exercise. The buyer has to apply the dates set out in the decision, establish the chargeable days for each location and refund excess amounts already deducted. The order gives the method for recalculation without announcing a single final refund amount. For the missing capacity it also changes the date from which the penalty period is counted. That adjustment affects the calculation while leaving the contractual liability in place.
The case illustrates why a single project capacity figure tells only part of a procurement story. The agreement covered 200 megawatts, the commissioning records account for 161.7 megawatts, and the difference became the subject of termination. Those milestones have distinct consequences for the buyer’s supply expectations and the developer’s accounts. The actions ordered in this case concern payments and contract enforcement. Any later procurement to replace missing supply would be a separate development.
Lead source date: 23 Nov 2026 · Source check: 24 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.