CESC’s Bikaner solar project starts commercial operation with 147 MW
Deshraj Solar declared commercial operation for 147 MW of its 150 MW project on November 21 after a certified trial run. The plant connects to the interstate grid at Power Grid’s Bikaner-III substation.
Press Listen to stream this report. No voice-model download or app is needed.
CESC says 147 megawatts of solar capacity have entered commercial operation at Karnisar Bhatiyan village in Rajasthan’s Bikaner district. Its November 21 disclosure identifies Deshraj Solar Energy, an indirectly owned subsidiary, as the developer of the 150 megawatt project. The operating portion connects to the interstate transmission network at Power Grid Corporation of India’s Bikaner-III substation. Press Trust of India reported the commissioning on Saturday, and ETEnergyWorld reported it on Sunday.
The declaration applies from November 21 and covers 98 per cent of the project’s stated capacity. CESC expects the remaining three megawatts to be commissioned by January 31, 2027. That date is the company’s expectation for the last portion. The November filing confirms the operating date for the first 147 megawatts and leaves the balance for a separate commissioning milestone. The split matters when tracking how much new capacity has actually entered service during a given month.
What the trial run established
Before its commercial operation declaration, the developer completed a trial run. According to the filing, the Northern Regional Load Despatch Centre, part of Grid Controller of India, certified that run on November 19. Trial operation tests whether a generating facility can run and connect to the system under the conditions that apply to it. The announcement gives the date and certifying body. It provides no generation totals for the trial or for the first days of commercial service.
The commercial operation date and later production figures answer different questions. The date identifies when the capacity entered service under the declaration. Metered megawatt-hours over a month or year show how much electricity it delivered. Solar output varies with the hours of sunlight and local operating conditions, so the stated megawatt capacity cannot establish annual generation by itself. For the same reason the latest filing cannot establish what customers might pay for power from the project. A utility comparing projects would also need delivery figures for the hours when its customers use the most electricity.
How Bikaner connects to the wider grid
The grid connection puts the Bikaner plant in the interstate network. Bikaner-III is the named connection point in CESC’s filing. A connection point tells planners where new generation enters the network. It does not show which buyer receives the contracted electricity or which path the power will take across the system at a given hour. Identifying who buys the electricity would require a purchase agreement or another disclosure that names the buyer. The November filing does not give that detail.
Separately, Power Grid’s management included the 400 kilovolt link between Bikaner-II and Bikaner-III among its commissioned transmission elements in an investor call held on November 10. That disclosure gives context for the wider network around the solar plant. The line and the generating project have their own commissioning records. CESC identifies the substation as the project’s point of connection, while the network operator and grid schedules govern how electricity flows across the wider system.
What remains to be reported
The next project milestone is the commercial operation declaration for the remaining three megawatts. A confirmation would bring the documented operating capacity to the full 150 megawatts. Over a longer period, reports of power generated and delivered would give readers a better sense of the project’s contribution than a single day’s declaration. For a grid planner, that is especially relevant when a growing share of generation comes from plants whose production is concentrated in daylight hours.
The notice does not set out a tariff, give a month of measured output or describe a battery installation for this project. Those are separate aspects of how a solar plant can serve the power system. The evidence available for Bikaner establishes a dated operating milestone, a successful certified trial and the grid connection for nearly the entire stated capacity.
Lead source date: 22 Nov 2026 · Source check: 23 Nov 2026. Older material is linked as background. The reports above are independently written; linked publishers are not affiliated with this publication.